PERMITS AND REGULATIONS:
- All utilities,
contractors, and/or sub-contractors must register with the Miami
County Utility Division.
- A permit
is required for ANY work performed in the right-of-ways in
Miami County.
- Each
permit must be completely filled out.
- A design
of the intended project must accompany the permit.
- A Miami
County map indicating the work area must be attached.
- The permit
must be submitted, allowing time for approval, before the
start of the project.
- The contractor
is responsible for contacting the Miami County Utility Division,
at 913-294-2674, a minimum of 24 hours before the start of the
project.
- The contractor,
or his representative, must have a copy of the approved permit
on site at all times.
- The contractor
is responsible for contacting the Miami County Utility Division
before the completion of the project.
- If it becomes
necessary to make changes to a permit, written notice must be
received at this office and approved by the utility coordinator
before any changes can be made at the site.
- All signing,
i.e. “Men Working”, etc., shall be properly displayed
on each project. The “Manual of Uniform Traffic Control
Devises” is to be followed.
- After a
project is completed, the easement shall be returned to as good
as, or better condition than it was before the start of the project.
Completed projects will be inspected and the contractor notified
if any additional cleanup is needed.
For complete
regulations: Accommodation Policy
Manual
If you have
any questions or concerns regarding the above, please do not hesitate
to contact the office at the above number. |